Construction of 132/33kV Substation at Umerkote

PROJECT OVERVIEW


Construction of 132/33kV Substation at Umerkote of

Client : Odisha Power Transmission Corporation Ltd.

Cost Of the Project : 32.03 Crore

 

STATUS OF COMPLETION


AS PER W.O.  :15.05.13

DATE OF COMPLETION : 10-04-2015

PERCENTAGE OF COMPLETION  :  100% completed